Latest projects

At present, the institute is engaged in reconstructing and technical upgrading of nuclear and thermal power plants, as well as in raising operational safety and reliability of nuclear power plants. The institute develops complete designs of gas turbine power plants (GTPPs), combined cycle power plants (CCPPs), and other types of power plants.

Among the institute’s latest projects are:

Power plant (part) Country Type of work
NPPs:
Zaporizhzhya NPP Ukraine
  • Design works on raising operational safety and reliability
  • Design of the spent fuel dry storage
  • Designs of treatment facilities for solid and liquid radioactive waste
  • Production of safety analysis reports
South Ukrainian NPP  
  • Design works on raising operational safety and reliability
  • Designs of treatment facilities for solid and liquid radioactive waste
  • Designs of treatment facilities for solid and liquid radioactive waste
Kudankulam NPP (Unit No. 1 & No. 2, 2х1,000 MW) India
  • Detailed design for the turbine building
  • Detailed design for the service standby boiler house and other service facilities
Novovoroneghskaya NPP (2х1,000 MW) Russia
  • Detailed design for the turbine building


Power plant (part) Country Type of work
TPPs and CHPPs:
Zmievskaya TPP Unit No. 8 (320 MW) Ukraine
  • Design, including detailed design, for reconstruction to restore the unit to the designed power output and to extend its service life by 15 to 20 years, replacement of the electrical precipitator
  • Design, including detailed design, for installation of a desulphurization system
Unit No. 9 (320 MW)   Feasibility study of reconstruction and technical upgrading
Tripolskaya TPP Unit No. 2 (320 MW)   Feasibility study of reconstruction and technical upgrading
Kharkovskaya CHPP-3  
  • Design of a 20 MW-generator set
  • Reconstruction of the service water supply system
Razdan TPP Unit No. 5 (320 MW) Armenia Feasibility study and design of unit’s modernization by adding gas turbines
Nassiria TPP Unit 4?200MW Iraq Reconstruction project of the distributed control system (DCS)
South Baghdad TPP Units No.3 & No.4 (2х50MW)   Design for replacement of the outdated equipment manufactured by General Electric
Obra TPP Unit 5х50MW India Reconstruction
Other power plants:
Gas Turbine Combined Cycle Power Plant (GT CCPP), 2х151.5 MW Alchevsk, Ukraine Design, including detailed design
Diesel engine power plant (DEPP), 25 MW Moscow, Russia Design
Pleikrong Hydro Power Plant (HPP) Unit 51 MW Vietnam Design of a hydro-turbine building